Accountability (71) Adequate documentation (7) ADR in procurement (4) Allocation of risks (6) Best interest of government (11) Best practices (19) Best value (15) Bidder prejudice (11) Blanket purchase agreement (1) Bridge contract (2) Bundling (6) Cancellation and rejection (2) Centralized procurement structure (12) Changes during bid process (14) Clarifications vs Discussions (1) Competence (9) Competition vs Efficiency (29) Competitive position (3) Compliance (35) Conflict of interest (32) Contract administration (26) Contract disputes (4) Contract extension or modification (9) Contract formation (1) Contract interpretation (1) Contract terms (3) Contract types (6) Contract vs solicitation dispute (2) Contractor responsibility (20) Conviction (4) Cooperative purchasing (3) Corrective action (1) Cost and pricing (13) Debarment (4) Determinations (8) Determining responsibility (37) Disclosure requirements (7) Discussions during solicitation (10) Disposal of surplus property (3) Effective enforcement requirement (35) Effective procurement management (5) Effective specifications (36) Emergency procurement (14) eProcurement (5) Equitable tolling (2) Evaluation of submissions (22) Fair and equitable treatment (14) Fair and reasonable value (23) Fiscal effect of procurement (14) Frivolous protest (1) Good governance (12) Governmental functions (27) Guam (14) Guam procurement law (12) Improper influence (11) Incumbency (13) Integrity of system (31) Interested party (7) Jurisdiction (1) Justification (1) Life-cycle cost (1) Limits of government contracting (5) Lore vs Law (4) market research (7) Materiality (3) Methods of source selection (33) Mistakes (4) Models of Procurement (1) Needs assessment (11) No harm no foul? (8) Offer & acceptance (1) Other procurement links (14) Outsourcing (34) Past performance (12) Planning policy (34) Politics of procurement (52) PPPs (6) Prequalification (1) Principle of competition (95) Principles of procurement (25) Private vs public contract (17) Procurement authority (5) Procurement controversies series (79) Procurement ethics (19) Procurement fraud (31) Procurement lifecycle (9) Procurement philosophy (17) Procurement procedures (30) Procurement reform (63) Procurement theory (11) Procurement workforce (2) Procurment philosophy (6) Professionalism (17) Protest - formality (2) Protest - timing (12) Protests - general (37) Purposes and policies of procurement (11) Recusal (1) Remedies (17) Requirement for new procurement (4) Resolution of protests (4) Responsiveness (14) Restrictive specifications (5) Review procedures (13) RFQ vs RFP (1) Scope of contract (16) Settlement (2) Social preference provisions (60) Sole source (48) Sovereign immunity (3) Staffing (8) Standard commercial products (3) Standards of review (2) Standing (6) Stays and injunctions (6) Structure of procurement (1) Substantiation (9) Surety (1) Suspension (6) The procurement record (1) The role of price (10) The subject matter of procurement (23) Trade agreements vs procurement (1) Training (33) Transparency (63) Uniformity (6) Unsolicited proposals (3)

Friday, December 9, 2011

Red tape or red herring?

It is a perennial ruse of political detractors and government agencies to blame the procurement process for the failure of politicians to appropriate and government to properly spend. Here's a current example.

MPs brand MoD’s procurement ‘extraordinary failure’
In a report published today, the PAC[Public Accounts Committee] found that, since the 1998 Strategic Defence Review, there had been an ‘extraordinary failure’ to produce necessary principal armoured vehicles. These include tanks and other reconnaissance and personnel-carrying vehicles.

The PAC blamed budget cuts, an overly complex procurement process and an ‘unrealistic culture’ where the MoD was demanding cutting edge technology it could not afford.

As a result, the armed forces will not have enough vehicles until at least 2025, making it more difficult to undertake essential tasks such as battlefield reconnaissance.

The reasons for this were ‘all too clear’, committee chair Margaret Hodge said, because £10.8bn had been taken from the armoured vehicles plans in the last six years as the department sought to balance its budget.

She added: ‘The MoD seems as far away as ever from establishing a clear set of affordable defence priorities. The problem for the armoured vehicle programme is that the department has yet to say how it is going to find the money to buy the vehicles it needs in future to carry out the full range of military tasks.’

Around £5.5bn will be spent on new armoured vehicles in the next ten years, but the report also warns this may be insufficient. It calls on the MoD to set out clearer procurement priorities, and to stop ‘raiding’ the armoured vehicles funding every time it needs to make savings.

As a result of the failure to produce vehicles through its core procurement programme, the department needed to be given £2.8bn by the Treasury to buy vehicles for the separate Urgent Operational Requirements programme.

The faster UOR process has been used to deliver mine-resistant vehicles for operations in Iraq and Afghanistan, but these are more expensive, the MPs said.

Responding to the report, defence minister Peter Luff said that ‘the armoured vehicle programme was left in a mess by the previous government’.

He added: ‘We are now sorting out their unrealistic and unaffordable plans by balancing the budget, investing real money in equipment and reforming outdated procurement practices.’
However, the minister said that the PAC was ‘misrepresenting the facts’ of some procurement deals.

‘It is not true to say the £1.1bnspent on armoured vehicles has not delivered any equipment. It has delivered Titan, Trojan and Viking vehicles, with Trojan and Viking used on operations in Afghanistan.’

He also said that the UOR process has been used correctly to ‘swiftly deliver world-class equipment to the frontline’.

While there may indeed be some problem with the procurement process, it was not detailed in this article. What was detailed is a failure of government to live within its means and aims. It then must resort to less competitive emergency procedures to compensate for its failure to properly plan and manage its acquisition needs, and, as this again reflects, emergency acquisitions tend to be more costly, if more expeditious, than competitive ones.

(For those unfamiliar with the term, "red hearing" refers to a
deliberate attempt to divert attention. See, Wikipedia here and here.)