Accountability (71) Adequate documentation (7) ADR in procurement (4) Allocation of risks (6) Best interest of government (11) Best practices (19) Best value (15) Bidder prejudice (11) Blanket purchase agreement (1) Bridge contract (2) Bundling (6) Cancellation and rejection (2) Centralized procurement structure (12) Changes during bid process (14) Clarifications vs Discussions (1) Competence (9) Competition vs Efficiency (29) Competitive position (3) Compliance (35) Conflict of interest (32) Contract administration (26) Contract disputes (4) Contract extension or modification (9) Contract formation (1) Contract interpretation (1) Contract terms (3) Contract types (6) Contract vs solicitation dispute (2) Contractor responsibility (20) Conviction (4) Cooperative purchasing (3) Corrective action (1) Cost and pricing (13) Debarment (4) Determinations (8) Determining responsibility (37) Disclosure requirements (7) Discussions during solicitation (10) Disposal of surplus property (3) Effective enforcement requirement (35) Effective procurement management (5) Effective specifications (36) Emergency procurement (14) eProcurement (5) Equitable tolling (2) Evaluation of submissions (22) Fair and equitable treatment (14) Fair and reasonable value (23) Fiscal effect of procurement (14) Frivolous protest (1) Good governance (12) Governmental functions (27) Guam (14) Guam procurement law (12) Improper influence (11) Incumbency (13) Integrity of system (31) Interested party (7) Jurisdiction (1) Justification (1) Life-cycle cost (1) Limits of government contracting (5) Lore vs Law (4) market research (7) Materiality (3) Methods of source selection (33) Mistakes (4) Models of Procurement (1) Needs assessment (11) No harm no foul? (8) Offer & acceptance (1) Other procurement links (14) Outsourcing (34) Past performance (12) Planning policy (34) Politics of procurement (52) PPPs (6) Prequalification (1) Principle of competition (95) Principles of procurement (25) Private vs public contract (17) Procurement authority (5) Procurement controversies series (79) Procurement ethics (19) Procurement fraud (31) Procurement lifecycle (9) Procurement philosophy (17) Procurement procedures (30) Procurement reform (63) Procurement theory (11) Procurement workforce (2) Procurment philosophy (6) Professionalism (17) Protest - formality (2) Protest - timing (12) Protests - general (37) Purposes and policies of procurement (11) Recusal (1) Remedies (17) Requirement for new procurement (4) Resolution of protests (4) Responsiveness (14) Restrictive specifications (5) Review procedures (13) RFQ vs RFP (1) Scope of contract (16) Settlement (2) Social preference provisions (60) Sole source (48) Sovereign immunity (3) Staffing (8) Standard commercial products (3) Standards of review (2) Standing (6) Stays and injunctions (6) Structure of procurement (1) Substantiation (9) Surety (1) Suspension (6) The procurement record (1) The role of price (10) The subject matter of procurement (23) Trade agreements vs procurement (1) Training (33) Transparency (63) Uniformity (6) Unsolicited proposals (3)

Thursday, June 6, 2013

Doth we protest too much? Methinks not

Protests delay Air Force contracts for firefighting, war planes
Protests have jumped 87 percent to a record 2,475 in the fiscal year ended Sept. 30 from fiscal 2006, which may be partly due to increased competition over declining awards in recent years. U.S. contracts fell about 4 percent to $512 billion last year from fiscal 2010, according to data compiled by Bloomberg.

The U.S. Air Force was set to deliver aircraft to the Afghan military in April. Its suppliers have only now started building them — after the contract was contested, canceled, re-bid, re-awarded, and contested yet again. Instead, they won’t be delivered until mid- to late 2014, as the U.S. plans to withdraw the last of its combat troops from Afghanistan.

The Air Force contract, with a maximum value of $950 million, was awarded to closely held Sierra Nevada Corp. and Brazilian subcontractor Embraer in December 2011. It has since been protested by Beechcraft. At the U.S. Forest Service, a protest of a contract for up to seven air tankers used to drop flame retardant means the 2013 wildfire season may be over by the time the planes are flying, said a spokesman for Sen. Mark Udall, D-Colo. Sierra Nevada officials had planned to supply the first of Embraer’s 20 turboprop aircraft in April 2013, said Taco Gilbert, a vice president at Sparks, Nev.-based Sierra Nevada, which is providing avionics and instruction under the contract.

For companies such as closely held Beechcraft, securing contracts is key as the Pentagon and other agencies slow spending. The company’s direct military contracts plunged about 68 percent to $331 million in fiscal 2012 from fiscal 2009, according to data compiled by Bloomberg. Beechcraft announced on Feb. 19 that it had emerged from bankruptcy protection. For Embraer, the award is a coup. The company is trying to tap the U.S. military market and expand its defense unit, which produced 15 percent of its 2011 sales.

There’s little the agencies can do to prevent the automatic, 100-day work delays triggered by protests to the U.S. Government Accountability Office, which arbitrates contract disputes. As a last-ditch effort, the government can supersede the stays with an override, which requires the officials to justify an urgent need or show that it’s in the best interest of U.S. taxpayers.

There have been no significant changes to the automatic delays in almost two decades. Congress in 2009 requested that GAO assess whether frivolous protests were rising. The office responded that attempts to discourage those challenges might backfire by adding costs and deterring “good-faith protests.”

Protests can serve as checks and balances to a sometimes opaque and flawed contracting process.

A prime example is the Air Force’s attempt to procure aerial refueling tankers. Chicago-based Boeing eventually prevailed against competitors European Aeronautic, Defence & Space Co. and Northrop Grumman.

Boeing’s first attempt at the $35 billion contract was derailed in 2004 by a scandal involving former top Air Force procurement official Darleen Druyun and then-Boeing Chief Financial Officer Michael Sears. Sears offered Druyun a job in October 2002 during the initial tanker negotiations. She was hired in January 2003. Sears and Druyun were convicted of violating federal conflict-of-interest laws.

Boeing was awarded the contract in February 2011, about 10 years after the Air Force first proposed the tanker-replacement program.

In March, the Air Force chose to override the latest protest from Wichita, Kansas-based Beechcraft, authorizing Sierra and subcontractor Embraer to resume work. Beechcraft has called the override unjustified, saying in a statement that the Air Force’s decision would lead to higher costs to taxpayers. It lost its challenge of the override at the U.S. Court of Federal Claims. The GAO has until June 17 to make a decision on the company’s protest of the contract.

Agency officials rarely use overrides. Even as protests soared, overrides have dropped by almost half to 33 in fiscal 2012 from 62 in fiscal 2006, according to GAO data obtained through a Freedom of Information Act request. Their waning popularity may be a result of increasing scrutiny from the Court of Federal Claims, which has let agencies know that it’s “not going to give them a free pass,” said Daniel Forman, a partner and co-chairman of the government contracting unit at the Washington-based law firm Crowell & Moring LLP.

Sue Payton, who was assistant secretary for acquisition at the Air Force from 2006 to 2009, said she used to build potential delays into the timeline for planning contracts. “Getting the requirements right up front saves you from protest hell,” Payton said.

The most effective way of avoiding challenges, though, is making sure the contracting process is fair and complete from beginning to end, according to current and former military officials. The Army tries to deter protests with contract solicitations that are “thoroughly scrubbed” to make sure they are clear, concise and compliant with federal regulations, said Matthew Bourke, a spokesman for the service. It also works to keep “a very open dialog with our industry partners,” he said in an e-mail.