Accountability (71) Adequate documentation (7) ADR in procurement (4) Allocation of risks (6) Best interest of government (11) Best practices (19) Best value (15) Bidder prejudice (11) Blanket purchase agreement (1) Bridge contract (2) Bundling (6) Cancellation and rejection (2) Centralized procurement structure (12) Changes during bid process (14) Clarifications vs Discussions (1) Competence (9) Competition vs Efficiency (29) Competitive position (3) Compliance (35) Conflict of interest (32) Contract administration (26) Contract disputes (4) Contract extension or modification (9) Contract formation (1) Contract interpretation (1) Contract terms (3) Contract types (6) Contract vs solicitation dispute (2) Contractor responsibility (20) Conviction (4) Cooperative purchasing (3) Corrective action (1) Cost and pricing (13) Debarment (4) Determinations (8) Determining responsibility (37) Disclosure requirements (7) Discussions during solicitation (10) Disposal of surplus property (3) Effective enforcement requirement (35) Effective procurement management (5) Effective specifications (36) Emergency procurement (14) eProcurement (5) Equitable tolling (2) Evaluation of submissions (22) Fair and equitable treatment (14) Fair and reasonable value (23) Fiscal effect of procurement (14) Frivolous protest (1) Good governance (12) Governmental functions (27) Guam (14) Guam procurement law (12) Improper influence (11) Incumbency (13) Integrity of system (31) Interested party (7) Jurisdiction (1) Justification (1) Life-cycle cost (1) Limits of government contracting (5) Lore vs Law (4) market research (7) Materiality (3) Methods of source selection (33) Mistakes (4) Models of Procurement (1) Needs assessment (11) No harm no foul? (8) Offer & acceptance (1) Other procurement links (14) Outsourcing (34) Past performance (12) Planning policy (34) Politics of procurement (52) PPPs (6) Prequalification (1) Principle of competition (95) Principles of procurement (25) Private vs public contract (17) Procurement authority (5) Procurement controversies series (79) Procurement ethics (19) Procurement fraud (31) Procurement lifecycle (9) Procurement philosophy (17) Procurement procedures (30) Procurement reform (63) Procurement theory (11) Procurement workforce (2) Procurment philosophy (6) Professionalism (17) Protest - formality (2) Protest - timing (12) Protests - general (37) Purposes and policies of procurement (11) Recusal (1) Remedies (17) Requirement for new procurement (4) Resolution of protests (4) Responsiveness (14) Restrictive specifications (5) Review procedures (13) RFQ vs RFP (1) Scope of contract (16) Settlement (2) Social preference provisions (60) Sole source (48) Sovereign immunity (3) Staffing (8) Standard commercial products (3) Standards of review (2) Standing (6) Stays and injunctions (6) Structure of procurement (1) Substantiation (9) Surety (1) Suspension (6) The procurement record (1) The role of price (10) The subject matter of procurement (23) Trade agreements vs procurement (1) Training (33) Transparency (63) Uniformity (6) Unsolicited proposals (3)

Tuesday, April 15, 2014

Settlement agreements do not abrogate procurement mandates

This GAO decision is interesting, not least of all because it sustained a protest (not the norm in GAO experience). 

 It is interesting because it indicates the type of critical analysis that should occur before a sole source contract is given out, but more interesting because it shows that when an agency proposes to give a sole source contract to settle a protest dispute, that decision is not binding; settlement agreements cannot vitiate procurement mandates. It gets fascinating with its description of the internal wrangling within the government and the influence of connections.   Finally, the case indicates the need to verify the claims of contractors pleading poverty and to justify exceptions to competition with valid facts and rationale; conclusory statements do not suffice for reasoned analysis.

As usual, I've excerpted, rearranged, paraphrased and left out citations to suit myself; read the decision at the link for a proper and independent recitation of the decision.

Matter of: Coulson Aviation (USA) Inc., File: B-409356.2, March 31, 2014
NextGen large airtankers are intended to replace the Forest Service’s use of “Legacy” large airtankers, which are generally much older, slower, and less reliable aircraft. The NextGen solicitation was intended to be the primary, but not the only, means by which the Forest Service met its modernization strategy goal of 18-28 modern large airtankers. The Forest Service’s procurement of NextGen airtanker services has a long and contentious history.

The NextGen RFP, issued as a small business set-aside, contemplated the award of multiple fixed-price contracts under seven contract line items (CLIN) for airtanker firefighting services on an exclusive-use basis. The CLINs, each of which had a 5‑year base period and five 1-year options, contained sub-CLINs providing the Forest Service with the option to add up to 2 additional airtankers in the second contract year and 2 more airtankers in the third through tenth contract years, for a possible total of 5 aircraft and 44 aircraft-years per line item.

Offerors were permitted to submit proposals for award of any or all of the CLINs, and were informed that awards would be made on a best value basis, considering price, structural integrity, maintenance, equipment, past performance, and organizational experience factors.

Nine offerors, including Neptune, Coulson, 10 Tanker, and Minden, submitted proposals. Coulson and 10 Tanker protested to our Office, challenging the agency’s price and technical evaluations, communications with offerors, and source selection decision; the GAO hearing official noted that the testimony thus far appeared to support the protesters’ arguments that the communications between the agency and various offerors were discussions rather than clarifications. Thereafter, the agency decided to take corrective action by reopening the competition.

While it was conducting the NextGen large airtanker procurement, the Forest Service also awarded a number of Legacy contracts for large airtanker services. The Forest Service awarded Neptune a Legacy contract for five P2V aircraft for 5-years, and for one P2V and one BAe-146[7] aircraft for a base year with four option years, at a total estimated price of $180,252,600. Shortly thereafter the Forest Service modified Neptune’s Legacy contract and added an additional BAe-146 aircraft for the 2013 fire season at a total estimated price of $4,960,200.

Neptune failed to win any NexGen award. Shortly after learning that it would not receive a NextGen contract award, Neptune informed the contracting officer of its intent to protest to our Office unless an “acceptable solution” could be worked out. Neptune’s protest triggered a stay of the NextGen contract awards pending our resolution of the protest.

Following a meeting between Neptune’s CEO, Forest Service FAM and AQM Directors and staffs, and USDA counsel, the parties engaged in a series of settlement discussions concerning the Forest Service’s noncompetitive award of a NextGen contract to Neptune pursuant to FAR § 6.302-3 (industrial mobilization) in exchange for Neptune withdrawing its protest.

Neptune’s CEO was quite familiar with the FAM Director and other agency officials, as the CEO had been the Forest Service’s AQM Director until his retirement. The record contains many letters and emails between Neptune and the Forest Service during this period, and reflects a number of conversations between Neptune’s Chief Executive Officer (CEO) and the Forest Service’s Director of Fire and Aviation Management (FAM) and Director of Acquisition Management (AQM). Neptune and the Forest Service had significant communications during the period between when Neptune learned it would not receive a NextGen contract and Neptune’s receipt of a sole-source contract.

The record indicates that the verbal representations of Neptune’s CEO concerning the firm’s financial viability were relied upon by the Forest Service when determining the agency’s actions. For example, shortly before or after filing its protest, Neptune’s CEO told the FAM Director that the company had made a significant investment in modern large airtankers and would go out of business without a NextGen contract award. At the Forest Service’s request, Neptune provided the agency with the firm’s financial projections. The Forest Service had USDA’s Rural Utilities Service (RUS) analyze Neptune’s continued financial viability based on the information provided by Neptune.

RUS provided USDA with its financial viability review of Neptune. The RUS noted that the information provided by Neptune did not include detailed expense projections or a balance sheet and cash flow projections for the next 5-year period. Id. The RUS also questioned whether Neptune had the ability to modify the payment terms of any of its existing long terms debts. Accepting the projected revenues and expenses as provided by Neptune on their face, RUS ultimately concluded that the only scenario in which the company could obtain a positive net income over the next 5 years was where Neptune received two NextGen contract awards in addition to its current Legacy contract.

The Forest Service and Neptune then entered into a written settlement agreement, under which the agency agreed to award Neptune a sole-source contract for two NextGen large airtankers in exchange for Neptune withdrawing its protest (and thereby ending the CICA stay of the NextGen contract awards). Our Office confirmed the withdrawal of Neptune’s protest and closed the file without rendering a decision on the protest’s merits.

Subsequently, the Forest Service realized that the sole-source contract promised to Neptune would require the approval of USDA’s senior procurement executive (SPE). Accordingly, the Forest Service informed the SPE of the settlement agreement that the agency had entered with Neptune, and requested that she execute a justification and approval (J&A) for the sole-source award.

The SPE did several things before taking any action on the Forest Service’s request. First, the SPE and her staff familiarized themselves with the NextGen procurement and the Forest Service’s requirements for large airtankers generally. The SPE made a series of requests of the Forest Service for additional information, including Neptune’s financial statements and balance sheets, Neptune’s Legacy contract, and documents related to the NextGen procurement. The SPE also engaged FI Consulting, an external auditing firm, to perform an independent financial viability analysis of Neptune.

FI found that Neptune had based its revenue projections for years 2-5 of the Legacy contract on the base-year rates instead of the higher, option-year rates set forth in the contract. FI also found that Neptune had based its revenue projections for the same period on the use of seven P2V aircraft, rather than six P2V and one BAe-146 aircraft (and the higher BAe-146 rates) as specified by the terms of the Legacy contract. After also finding Neptune’s expected costs to be lower than the company’s projections, FI concluded that Neptune would have the financial capacity to operate and continue performing on its in-place Legacy contract with the Forest Service through, at a minimum, calendar year 2016, without any further contract awards.

The SPE then asked FI to perform a comparison of its conclusions with those of RUS. FI found that the fundamental difference was that RUS had solely relied on Neptune-provided financial projections while FI had had access to a wider range of information that allowed it to develop its own projections. One such example was the difference in Neptune’s revenue projections detailed above. Similarly, the cost projections developed by FI assumed, per the terms of the Legacy contract, that Neptune would be reimbursed its fuel costs in addition to aircraft flight rates. By contrast, “Neptune did not provide any detail with its cost projections to RUS, so it is unclear if fuel is included, or if government reimbursement is considered.” In a subsequent meeting conducted by the SPE, RUS employees generally agreed with the FI findings and conclusions.

Based on her review of all information, including the FI financial analysis, the SPE concluded that the planned sole-source contract award to Neptune for industrial mobilization reasons was not presently justified (“Neptune didn’t need a contract”). Consequently, the SPE refused to approve the sole-source award to Neptune. the Forest Service informed Neptune that the SPE would not approve the sole-source contract contemplated by the parties’ settlement agreement, insofar as the financial analysis of the additional documents provided by Neptune indicated that the company was financially viable without such a contract.

For the next three months the Forest Service tried to reach an alternative settlement agreement; Neptune, however, rejected all offers that differed materially from the terms of the parties’ settlement agreement. Moreover, Neptune repeatedly informed the Forest Service that Neptune would file a lawsuit against the agency if the agency did not satisfy the terms of the parties’ settlement agreement.

Various internal meetings also took place among senior Forest Service and USDA officials, including USDA’s Undersecretary for Natural Resources and Environment (NRE Undersecretary) and the Assistant Secretary for Administration (ASA), in an attempt to resolve the Neptune matter.] The SPE testified that, in the meetings she attended, she heard no rationale advanced for a sole-source award to Neptune that she had not previously considered, and no rationale that she believed properly justified such an award.

At that time, the request for approval of the J&A was elevated to the ASA, a level above the SPE within the agency’s hierarchy. The SPE had several conversations with the ASA in which she recommended that he not approve the J&A as there was not a valid justification for doing so. Specifically, in making her recommendation the SPE stated as follows:
General – Public policy, the Competition in Contracting Act, and the FAR promote competition to ensure a fair playing field for firms interested in doing business with the Federal government. Competition encourages innovation and lower prices. Noncompetitive awards should be limited to only what is needed to achieve the objective, in this case to maintain a vital source of supply . . . . In this case, we have a competitive field and recently awarded multiple contracts on a competitive basis to five firms from a pool of eight firms that submitted proposals on the solicitation.

Rationale – The rules do not support the issuance of a sole source award based on the fact that a firm did not win a competitive procurement or in exchange for a particular action, such as the withdrawal of a protest or [Freedom of Information Act] request.

Neptune’s Financial Stability - . . . [A]n independent financial review revealed that Neptune has the financial capacity to operate and continue to supply planes under the current contract with no further contract awards. There’s no evidence to support the assertion that Neptune would not be able to meet an emergency need for aircraft.

Maintain Capacity and Employee Skills - The [Forest Service] currently has a supplier base of five firms on the Next Gen contract. These firms are building both capacity and employees skills. [Forest Service] also has two firms on the legacy contract that can supply planes. Neptune has supplied Next Gen type planes on the existing legacy contract and others could be added provided it is within the scope of that contract.

Balanced Supply Source – It is not clear how a noncompetitive award to Neptune would create a balanced source of supply . . . . It seems like if we’re interested in creating a balanced source of supply we would award more air tankers to the other legacy contractor, Minden, or add more air tankers to the current Next Gen contractors versus issuing a noncompetitive award to an unsuccessful offeror.
The SPE was not the only agency official providing advice to the ASA. The NRE Undersecretary recommended the award of a sole-source contract to Neptune. AR, Tab 43, NRE Undersecretary Memo to ASA, Nov. 26, 2013, at 1-2. The NRE Undersecretary emphasized the importance of large airtankers for wildland firefighting and the Forest Service’s need for additional airtankers, particularly with regard to the 2014 fire season. Id. at 1. The NRE Undersecretary also stated that, insofar as USDA counsel had determined that awarding a sole-source contract here was permitted and Neptune had airtankers available, he strongly recommended the award of two NextGen aircraft to Neptune for up to 10 years.

On December 9, the ASA executed a J&A for the sole-source award to Neptune for two NextGen aircraft. The J&A stated the following justification for the sole-source award to Neptune:
Pursuant to FAR 6.302-3(b) [sic] (i),(ii),(iii) and (vi) [sic], the use of the industrial mobilization exception to the requirement to use full and open competition is appropriate when it is necessary to--(i) [k]eep vital facilities or suppliers in business or make them available in the event of a national emergency; (ii) prevent the loss of a supplier’s ability and employees’ skills; (iii) maintain an acceptable balance of sources; and (vi) [sic] provide for an adequate industrial base by dividing the supply among two or more contractors. The Forest Service has determined that based on all the above reasons, it has become necessary to invoke this authority with respect to Neptune Aviation, whose resources and equipment must be available to provide key services if the Forest Service is to successfully fulfill its mission.
Although factual assertions were given in support of the justification, absent from the J&A was any discussion regarding Neptune’s need for a sole-source contract to remain a source of supply.

A noncompetitive contract was awarded to Neptune on December 12. Although the J&A supported an award of two NextGen large airtankers, the contract actually awarded to Neptune permitted (by mutual agreement) the addition of two more airtankers to the first CLIN and three more airtankers to the second CLIN in each contract year. These protests followed publication of the sole-source award to Neptune in FedBizOpps.

Our review of an agency’s decision to conduct a noncompetitive procurement focuses on the adequacy of the rationale and conclusions set forth in the J&A. Where a federal agency makes a sole-source award for purposes of maintaining a particular source for an item or service, concern for maximizing competition is secondary to the agency’s industrial mobilization needs. Decisions as to which suppliers should be included in a mobilization base, and which restrictions are required to meet the needs of industrial mobilization, involve complex judgments that are generally left to the discretion of the federal agencies. We will question those decisions only if the evidence shows that the agency has abused its discretion. We will sustain a protest, however, where an agency’s J&A fails to demonstrate that it is in fact necessary to award a contract to a particular source for industrial mobilization purposes.

As explained below, the record does not support the USDA’s decision to award a sole-source contract to Neptune for industrial mobilization purposes. Rather, the record demonstrates that the sole-source contract--promised by the Forest Service in exchange for Neptune’s withdrawal of an earlier bid protest--was without a reasonable basis.

The protesters contend that the sole-source award to Neptune was improper, insofar as the agency promised to enter into the contract in exchange for Neptune withdrawing its protests of the NextGen contract awards. In this regard, the protesters claim that the agency’s actions have been motivated by the desire to fulfill the terms of a settlement agreement and to avoid a lawsuit by Neptune for allegedly breaching that agreement. The protesters argue that the agency “put the cart before the horse,” and agreed to settle Neptune’s protest before properly determining that the promised sole-source award complied with CICA. The USDA does not dispute that its consideration of a noncompetitive award to Neptune was motivated by its promise of a sole-source contract in exchange for Neptune withdrawing its bid protest and thereby ending the CICA stay that then precluded the Forest Service from fielding NextGen large airtankers for the 2013 fire season.

A settlement agreement promising award of a contract on a sole-source basis in exchange for abandoning ongoing litigation, such as a bid protest, is not a permissible basis for restricting competition and excluding potential offerors. Quite simply, the existence of a settlement agreement does not permit a contracting agency to act in ways not otherwise permitted by applicable statutes and regulations.

Nevertheless, USDA argues that it did not act improperly because the sole-source award complied with all applicable procurement statutes and regulations. The Forest Service entered into a settlement agreement with Neptune on the basis that the award of a sole-source, NextGen-type contract was necessary to maintain Neptune as a vital source of large airtankers. The independent financial analysis subsequently performed by FI on behalf of USDA concluded that Neptune did not require the award of a sole-source contract to remain financially viable. Nothing in the record refutes FI’s conclusions, nor is there any evidence to suggest that Neptune intends to go out of business now merely because its future prospects appear uncertain. In sum, while the agency may not have entered into a settlement agreement promising to disregard applicable procurement statutes and regulations, the agency’s subsequent decision to award a sole-source contract to Neptune so as to comply with the terms of the settlement agreement and avoid a Neptune-threatened lawsuit was without a reasonable basis.

The agency has acknowledged that it was initially concerned that Neptune would “immediately go out of business during the 2013 fire season, leaving the Forest Service without any of the Legacy air tankers Neptune supplied under the contract awarded March 27, 2013.” The agency admits, however, that ultimately it concluded there was no concern with Neptune’s present viability, but only with its viability after 2017. Consequently, the agency argues, the J&A was not grounded on the agency’s belief that Neptune would immediately go out of business without a NextGen contract, but was based on its concern with Neptune’s continued availability as a large airtanker supplier after 2017 when its Legacy contract expired. However, changing its focus during the course of the protests, the agency has also argued that its actual concern is whether it could obtain sufficient NextGen airtankers for the 2014 fire season. In this regard, the agency maintains that it cannot tolerate any further delay in acquiring additional NextGen airtankers for the 2014 fire season. The Forest Service contends that this immediate need for additional NextGen airtankers provided it with “an industrial mobilization need in December 2013” when it decided to award Neptune a sole‑source, 9-year contract for NextGen airtanker services.

Based upon on our review of the record, including the J&A, its supporting documentation, the agency’s submissions in response to these protests, and the testimony of the agency’s representatives at the hearing held at our Office, the agency has failed to demonstrate that Neptune requires a sole-source contract to remain a source of large airtanker services for the Forest Service. Although the J&A documents the agency’s belief that Neptune is, presently, a vital supplier of large airtanker services under Neptune’s Legacy contract, the J&A is devoid of evidence or analysis supporting the need to provide Neptune with a sole-source award for the firm to remain a viable source of supply. Rather, the record demonstrates, as acknowledged by the agency, that Neptune is presently financially viable and is expected to remain financially viable through the term of its Legacy airtanker contract (2017). Moreover, apart from Neptune’s own unsupported statements and the anecdotal views of various agency officials, the record contains no analysis or evidence of Neptune’s financial condition after 2017. While the agency contends that the J&A did not rely on the FI financial analysis to assess Neptune’s long-term viability, neither did the agency rely on any other information when making such an assessment. In fact, there is simply no record--in the J&A or otherwise--of any assessment by the agency of Neptune’s long-term viability.

Additionally, the agency’s apparent belief that an immediate need for NextGen airtankers in 2014 justified the award of a sole-source, 9-year contract on the basis of industrial mobilization is not supported and has no rational basis. The industrial mobilization exception to competition requirements may be used where an agency determines that “it is necessary to award the contract to a particular source . . . in order . . . [t]o maintain a . . . [vital] supplier . . . .” FAR § 6.302-3(a)(2)(i). As noted above, no reasoned analysis has been presented to support a determination that a 9-year, sole-source contract was required to maintain Neptune as a source. To the extent the agency believed an urgent need for large airtanker services would justify a noncompetitive 9-year contract, there is no analysis or explanation in the record demonstrating that this is so.

Moreover, given the contract options available to the Forest Service under the competitively-awarded NextGen contracts, Neptune may no longer represent a vital source that must be maintained by the Forest Service after 2017. While agencies have authority to make noncompetitive awards when necessary to maintain vital sources, they do not have authority to make noncompetitive awards merely because an offeror is unsuccessful in a competitively-conducted procurement, or because such action was promised in a settlement agreement. Neptune would undoubtedly prefer the financial security that would accompany a long-term NextGen contract, but this is simply not the standard by which an agency is permitted to make a noncompetitive award for industrial mobilization purposes.

As a final matter, in addition to the fundamental lack of support for the J&A’s premise that Neptune now requires a 9-year sole-source contract in order to maintain the firm in the future as a vital supplier of aircraft, the record reflects that the J&A was premised on materially inaccurate information. As stated above, our review of an agency’s decision to conduct a noncompetitive procurement focuses on the adequacy of the rationale and conclusions set forth in the J&A. The adequacy of the rationale and conclusions set forth in the J&A is dependent on the completeness and accuracy of the information included in the J&A. We find the J&A to be incomplete and inaccurate in certain key regards. Alternatively, if the J&A was accurate here, then the contract awarded to Neptune impermissibly exceeded what the ASA had approved. This is significant because where, as here, an agency proposes to award a sole-source contract under the industrial mobilization exception to the general competition requirements, the amount being ordered must meet--not exceed--the objectives of this authority.

Similarly, when considering alternative sources and the market research regarding such sources, the J&A states that “[t]here are no certified [large airtankers] currently available that aren’t already under contract with the Forest Service. Aircraft capable of meeting these standards and requirements are not readily available and would take a considerable amount of time to be developed and operationally ready for service.” This statement is also factually inaccurate.

The fact that the J&A was inaccurate with regard to alternative sources is also important because where, as here, an agency proposes to award a sole-source contract premised on the vital nature of a supplier, it must accurately consider whether the industrial base can be maintained without resorting to noncompetitive procurements. While the agency argues the fact that other contractors may have airtankers available to perform Neptune’s contract to be irrelevant here, we fail to see how the agency can reasonably find Neptune to be a vital source without accurately considering all sources.